Springfield Ave. Water Main Update from NJ American Water Company 2-13-2020

This update is provided by NJ American Water Company:

Night Work

Service work down toward Maple should complete Tuesday, Feb. 18.

Next Wed. thru Fri., Feb. 19 – 21,  they will tie-in at Passaic St. and at Livingston Ave.

The following week, Feb. 24 – 28, they will be doing hydrant removal.

 

Day Work 

During the next 2 weeks they will complete the side street tie-ins out of the  Springfield Ave traffic lanes.

They expect to do clean up and demobilization on  March 2 and 3.

 

 