Fairmount Road Water Main Replacement Project to Begin

New Jersey American Water main replacement project to start soon

ABOUT THE PROJECT
At New Jersey American Water, we’re committed to providing our customers with safe, reliable water service. This requires investing in our treatment and distribution systems, and one of these projects is about to take place near you. The project involves replacing aging water main, as well as utility-owned service lines and fire hydrants along the pipeline route.  

Weather permitting, the work is scheduled to begin on or about Nov. 21 with service test holes for one or two days.  The water main replacement is scheduled to start on or about Nov. 28.  The project is expected to be completed by mid-December.  Work will take place from 7 AM – 4 PM, Mon. – Fri.