Over the next week, our PSE&G crews will be in New Providence replacing main and services to the following streets, weather permitting;
Crew one: Yarmouth Drive installing main and connecting services
Continuing onto Hathaway Drive upon completion
Crew two: Grant Avenue installing main and connecting services
Continuing onto Hickson Dr upon completion
Crew three: 2nd Street installing main and connecting services
If you have any issues, please call the Gas Construction customer hotline: 1-833-661-6300 or email: Jeannemarie.Ryder@pseg.com.
Please also check the New Providence Gas Construction webpage: