The following have been completed on Fairview Avenue:

  • Drainage Work
  • Survey field work
  • Curb
  • Base Repair
  • PSE&G replaced gas lines
  • Milling and Paving
  • Speed Table
  • Striping

Outstanding punchlist items will be addressed in the Spring 2022